Colleyville to give Glade Road a makeover

0

Construction of the Glade Road Paving and Drainage Improvements Project is scheduled to begin the first week of January.

These improvements include:

  • additional turn lanes at the Glade Road and Heritage Avenue intersection
  • dedicated left turn lanes on Glade Road at Prestwick Drive and Roberts Road, Queensbury Way, Auburndale Avenue, and Martin Parkway, and
  • a 10-feet-wide trail, water line improvements and a drainage system

The first phase includes construction at the Glade Road and Heritage Avenue intersection. The following phases include reconstruction of the southern half of Glade Road, which includes the existing road and finally the northern half of the roadway. Construction is anticipated to be complete in the summer of 2007.

For additional information, please call the City of Colleyville Engineering Department at 817.503.1090.

Source: City of Colleyville