Content from our friends over at TheRockwallNews.com
Wednesday, June 10, 2009
Oncor wants electricity customers to pay $93 million for smart meters they’ll never use
The Oncor electricity delivery company wants its residential customers to pay $93 million for obsolete “smart meters” the company ordered but customers will now never use because they’re not up to state regulations.
The issue is part of a pending Oncor rate increase which, if approved by the Public Utilities Commission later this year, will increase the average customers’ bill by over five dollars.
In January the company already began charging customers an extra $2.21 per month to pay for new meters that do comply with state regulations - regardless of whether or not they have received a new meter.
The surcharge, which will be collected for 11 years, applies whether or not Oncor customers have received a new meter. The rollout won’t be completed for three years.
Any increase would mark the second time this year that Oncor customers had been told to pay for advanced meters.
The proposal to recover costs for the obsolete meters is a focal point for opponents of the rate hike–among them consumer groups, a coalition of cities and the PUC legal staff.
“These costs should be borne by Oncor, not by ratepayers,” PUC staff attorney Patrick Peters III asserted in a rate case filing.
In an advisory ruling issued last week, two administrative law judges ruled that Oncor is only entitled to part of the amount because its meter purchases were “imprudent,” purchased prematurely and so customers shouldn’t have to foot the whole bill.
Nearly 900,000 smart meters were bought before the Texas Public Utilities Commission issued operating standards, and officials say the meters are not in compliance.
On the other hand, the company thinks their customers should pay for the meters since the equipment was designed to help reduce utility costs for consumers.
All of the smart meters are currently in use and will be replaced with new meters that are in compliance if the cost of those meters can be recovered, said Oncor spokesperson Catherine Cuellar.
The first-generation smart meters will then be reallocated and used for other projects, such as city street lights, where meters do not require the same customer functionality.
Cuellar added that the original meters were bought at the request of the state and that in order to fund the second-generation meters, the company needs to recover the cost of the first-generation meters as well. If that cost cannot be recovered, Cuellar said the original first-generation smart meters will continue to be used by customers at their residences.
“If we didn’t feel as though they were a prudent investment,” company spokesman Chris Schein said, “we would not have sought recovery.”

Pegasus News content partner - TheRockwallNews.com
Email
|
Print
|
Comment
|
Tell us your story
|
- »Rockwall gets seafood with Catch 22 Seafood Market & Grill
- »A brown poodle has been found in the Rockwall area
- »Spine Team Texas hosts benefit at new Rockwall facility
- »Interesting new Restaurant Ava with lots of foodie signifiers to open in Rockwall on Tuesday
- »Rockwall Community Playhouse opens My Fair Lady this week
-
»Lewisville resident breaks Guinness World Record for longest drum roll
-
»Collin County Commissioners Court to hold public meeting at Melissa church
-
»Oncor employees attacked at two separate Dallas homes
-
»Collin County officials enhancing revenue through constable traffic patrol
-
»Accusing nurse allegedly had affair with in-office, masturbating pediatrician from Fort Worth


"Cuellar added that the original meters were bought at the request of the state and that in order to fund the second-generation meters, the company needs to recover the cost of the first-generation meters as well. If that cost cannot be recovered, Cuellar said the original first-generation smart meters will continue to be used by customers at their residences.
“'If we didn’t feel as though they were a prudent investment,” company spokesman Chris Schein said, 'we would not have sought recovery.'”
Why isn't the State paying for them, rather than ratepayers, who are now paying for the "approved" version?
Schein apparently went to a business school where the laws of physics were suspended.
Oudekerk Anonymous
5 months, 2 weeks ago
Link to this comment | Suggest removal
In Saturday's Dallas Morning News, the paper ran a correction to this story stating Oncor's first generation automated meters are currently in use and will continue to be used for streetlights and other functions where consumer functionality of the newer advanced digital meters isn't needed.
Catherine Cuellar Verified
5 months, 2 weeks ago
Link to this comment | Suggest removal
and even though my power is still out due to the storm I bet I still have to pay my 2 bucks this month ... not to mention the double-billing last month (grumble, grumble)
David Goodspeed Verified
5 months, 2 weeks ago
Link to this comment | Suggest removal
So, is Oncor a provider, or do they just control how the electricity comes to your home? Basically, can you just switch to (shameless plug) Green Mountain and avoid the whole surcharge, as well as indirectly showing 'em who's boss?
Pavel Lishin Verified
5 months, 2 weeks ago
Link to this comment | Suggest removal